The activities mainly consisted of:
Mechanical and piping installation works for Tank pit 203, interconnecting piping works with 32 tanks and 5 truck loading stations. The works are executed in a greenfield area.
- Prefabrication piping works
- Construction of steel modules
- Installation of piping works in modular piping bridges, including tracing and insulation
- Transport of 7 pipe bridge modules from prefabrication area to Chane terminal Botlek by barge
- Installation of 7 pipe bridge modules on location and interconnecting piping works
- Installation of Tie-ins to existing systems
- Hydro testing
- Tracing and insulation works